Approving Center in PWA 2010 is taking lot of time to load

PWA is on the local server only even so PWA is taking more than ii-3 mins to load. Is there whatsoever manner nosotros can reduce this?

Regards

Deepak Dharmpurikar


Deepak Dharmpurikar


Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 60+ minutes.

Honey Sirs,

I need your support over the post-obit MS EPM 2013 consequence:

Publication of the big-sized Enterprise projects from Projection Professional 2013 to Project Server 2013 takes about xxx+ minutes. Nosotros need to reduce this total publication fourth dimension downward to acceptable working values 10+- minutes.

Surround information:

Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free deejay space, OS Windows Server 2012 Standard Edition x64 Service Pack one, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) practical.

Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free infinite, Bone Windows Server 2012 Standard Edition x64 Service Pack i, MS SQL Server 2012 x64 SP 1 Enterprise Edition.

We accept 1Gbit LAN between APP, DB server and 1Gbit LAN betwixt APP and Proj Prof Customer.

Yep, we are on the way of migrating to the Prod environs with three-tiered compages (with SP1 slipstream and CU December 2014 applied), but this issue alsopresents there.

Project's file information:

Tasks in the file: [~4900], resource in the file [~396] enterprise chore's custom fields used in the file [~23].

Projection save process for this new project would last nigh 7 minutes. Project publication would last about 47 minutes. We noticed that tasks synchronization process took about i second for each ~two,5 tasks, to add them to the sharepoint tasks list. And then for all 5148 tasks information technology took about 5148/iii/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks relevant for new sharepoint site cosmos.

Case one: Issue description:

During the Enterprise project's file salvage and publication nosotros have the following sharepoint 2013 log letters:

07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (Persisting list changes). performing time = 376 .068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd

07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (Persisting list changes). performing time = 361 .652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd

It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,five min) for each task update during project publication. And we also have another log file that shows that most 0,seven sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each chore in project file to project server. So total save and publication time more then lx+ minutes for that project file. The same upshot nosotros take even if user didn't do any changes at the projection file.

We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do non use sharepoint tasks lists, but the synchronization betwixt MSP Plan and SharePoint tasks list works at any example.

Case 2: Issue description:

- For the second test we created a new project with new sharepoint projection's site on basis of our «outcome» project, with total amount of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site upward to 6000 items in it – standard limits for sharepoint view list – 5000 items).

- Projection salvage procedure for this new project would final about vii minutes. Projection publication would last about 47 minutes. We noticed that tasks synchronization procedure took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. And so for all 5148 tasks it took nearly 5148/3/threescore =  34 minutes. Other xiii min was used for reporting database publication and other tasks relevant for new sharepoint site creation.

-Then nosotros deleted the tasks list for that new test project from the sharepoint site and republish the projection programme one more time. This time projection relieve procedure took about 7 minutes, projection publication about 2 minutes and 3 minutes for other relevant queue jobs. And then full fourth dimension is 12 minutes.

Every bit a determination: yes, nosotros take determined the verbal trouble - during synchronization process (from Projection Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At whatever example, synchronization volition copy ALL of them from Project Server to SharePOint chore's list.

Our workaround is to disable the task's synchronization for such big-sized projection plans:

– to delete the SharePoint «tasks» listing at the SharePoint site tied with projection plan.

- or deattach the SharePoint site from the project programme.

Thank you for reading this topic, please if you besides forced with such issue provide us any known workaround or maybe whatever official response \ feedback from MS nearly it.

Thanks in advance,

Best Regards, Andrey

I receive "WorkflowCannotStartWorkflow" erorr, though the Project Type is not associated to whatever workflow!

How-do-you-do,

I continue receiving an erorr mesaage says "WorkflowCannotStartWorkflow" though the Project Type is not associated to workflow!

Following is an image of the erorr mesaage:

Any suggest please ??











User specific task taking hours to complete and some times go failed in Projection Server 2010

Multiple Windows

I use 2 monitors, my laptop and an extra monitor. I want to take two separate instances of MS Project (2010) open, one in each monitor, and so I tin can view both together. I've been unable to reach this. Anyone know how?

Publishing a Projection Plan causes a full crawl of all Project sites in drove and pegs retentivity at 100% utilization

Publishing a Project Plan causes a full crawl of all Projection sites in the collection.  This causes memory on the WFE running the crawl to slowly creep upwards (takes nigh 15 mins) until all server memory is used.  This in turn causes PWA client timeouts\errors as there is no available retentivity to procedure other requests.  I've checked ULS while this is occurring and the following entry is logged thousands of times "GetSecurityChangesFromSharePoint : Site Id = '77415162-5a9c-461e-9c36-6f5aded60c4b'. db id = '4fed8194-d804-47aa-ba81-58e92a168c03'. Group membership/security policy changes detected. All furls in the in the site drove volition exist crawled."

Even though nosotros are load balanced users connecting to the second WFE may still experience slow response while the crawl is running.  To brand matters worse if another project is published while the first crawl is running the whole process may be kicked off once more; imagine what happens on Friday afternoons when everyone is trying to update their plans before the weekend.  I've seen the memory peak for over an hour at a time every bit multiple projects are published, adversely affecting PWA and publish functioning.

I've checked the "Projection Server: Synchronization of SharePoint Server permissions to Project Spider web App permissions job for Projection Services"timer task it is scheduled to run every infinitesimal (out of the box).  It evidently isn't running every minute otherwise this process would never end every bit a full clamber takes about 15-17 minutes to consummate.

Why is a total crawl being washed with nearly every project plan publish, this makes no sense.  It should merely be itch the specific site for the project you just published rather than crawling the whole collection each time.  Complete site collection crawls should simply be running afterward midnight when user traffic is low.

Is anyone else seeing this issue?  I've been hitting the web and forums to see if anyone else is experiencing this issue and I haven't found a single striking.  I started noticing this behavior about two weeks ago still it could take been going on for old as PWA operation isn't affected every time the memory peak occurs.

I don't think seeing this behavior prior to installing the September 2014 CU.  I've checked all the published CUs afterwards September 2014 and it isn't mentioned equally a fix in whatever of them.  The only way I can encounter to prevent this is to disable the Projection site sync feature and so practise manual syncs equally needed.  This is manifestly not a fix as I have no desire to be a sync monkey.

If I don't get any helpful responses from this forum I volition open up a ticket with Microsoft as this is non desirable beliefs.


Frank Miranda Florida Infirmary MIS

project server 2013-Task Eye- My Assignments View- how to brand default to all users

How-do-you-do,
Project Server 2013-On Premise
How I can a custom View(no Gantt Chart-to adjust infinite) equally a default view in Task Center ?

Thnks


Trying to figure out how to enter time for resources that dont have access to PWA

I am fairly new to Project Online and have configured about of my server settings.  I have created a projection and set the enterprise resources then published the projection to PWA. In one case there the users with Project lite and project managers tin can run into the tasks that take been assigned to them and in that location fourth dimension sheets likewise brandish the tasks. I can't seem to figure a manner to enter time in for all the other resource that practise not have some sort of subscription. Well-nigh of these resource are labor positions and do not take access to a computer to input their time. This would need to be done daily past the store supervisor. I didn't know if this was possible or if I would manually need to enter the that data for those resources in the actual work department in project managing director.


"An unknown fault" has occurred in status report in project server 2013

"An unknown error" has occurred in status report in project server 2013

problem with the% divergence from Project Server 2010 field

hello

I have a problem with the% deviation from Project Server 2010 field.
Inside a file or project, this project contains tasks.
Each chore has completed the field% deviation.
Inside the row "Summary" in the field of% departure does not perform the sum of all fields of tasks.
Only occurs on certain projects, these projects have the view of PR Progress Report
Anyone know happens?

cheers very much

How to get the original Projection Creator

Hi

The project possessor for i of the projects was updated sometime ago. Is there a fashion to find who the original creator of the project was?

Thanks

meeta

Queue Error PreparePSProjectPermissionSynchronization.PreparePSProjectPermissionSynchronizationMessage

The queue gives a failed but non blocking correlation on project publish:

GeneralQueueJobFailed (26000) - PreparePSProjectPermissionSynchronization.PreparePSProjectPermissionSynchronizationMessage. Details: id='26000' name='GeneralQueueJobFailed' GroupType='PreparePSProjectPermissionSynchronization' MessageType='PreparePSProjectPermissionSynchronizationMessage'

Some details:

  • On Bounds instance, non Office 365
  • The continued sites are not sub sites of other project sites
  • Service Pack one and Feb 2015 CU has been installed
  • User Profile service is running and all AD accounts be
  • Not all projects have the mistake
  • Switched on verbose logging and no AD account is flagged.
  • I of the projects doing this only has a single global resources that is not even an AD user.
  • Distributed cache is running and properly connected with App Fabric

Any suggestions on how to resolve this?
I switched of the "User Sync settings" for now not to get the mistake notification not to be emailed to the PM's.


Michéle Johl

fourth dimension charged is showing up in projection but non in timesheet?

The chore which the time was charged was set to unpunished  after resources charged time to it, Now its showing up in project bodily but not in  resource timesheet and the same hours are showing up in adjacent line of timesheet

IS information technology possible that system automatically shifted hours to next chore of other project?

How to remember Timesheet Approver by query

Howdy,

I'm retrieving timesheet manager proper name from ResourceTimesheetManagerUID field in MSP_EpmResource_UserView view. Simply, If a user change timesheet director while submitting fourth dimension canvass I'm unable to admission it.  I tried searching in reporting DB documentation but did not find anything over there. Tin can someone let me know the field where this info is stored?

Thanks

Indu

Unable to change Task Start/End Dates

How-do-you-do All,

(Project Server 2013 w/ SP1 + December CU)

Nosotros have found a programme that has a task with erroneous start/stop dates x/ten/32 etc. The task has no planned piece of work or actual work nor does it have any dependencies or external links.

When we effort to reset the dates, we go a message from project server stating that the changes cannot be made as Project Server is gear up to allow only actual work be entered through timesheets or my piece of work.I have tried to replicate this in another plan with the same constraints etc simply I cannot.

The message is the aforementioned from project Spider web App and project prof.

Any ideas?

Tks,

Shane


Shane O'Hanlon (Accenture)


Bulk Update Project Sites (PS2010) Non Working

Hey folks, I've a problem where I click on an Issue of a Project, and I get the dreaded "File Non Found" SP/PS error.  Per documentation, running the Majority Update Project Sites tool should resolve the trouble for those projection sites.  Unfortunately, a number of sites that have Issues still show this problem.

Of involvement is that prior to this problem, an AAM alter was done, for example,www.my-domain.com to world wide web.mydomain.com.  The errors related to the higher up are due to the Issue still looking for thewww.my-domain.com/pwa site, which no longer exists.

It looks like an AAM change also caused this outcome...but I'm not 100% certain.

Has anyone seen behavior like this?

Tin information exist changed directly in the databases to facilitate the new URL?  If then, which URL?

Thanks folks, much appreciated.

- M


Michael Mukalian | Jan 2010 - December 2010 MVP SharePoint Services | MCTS: MOSS 2007 Configuration | http://www.mukalian.com/weblog


"Level Resource" hangs

Hi all,

when I try to level the assigned resources of our enterprise
project with an enterprise resources pool MS Projection hangs (not responding).
This failure occurs in 2 of 10 cases

Accept veryone some ideas how tin can I ready this effect?

Thanks


Project Server 2013 Note Field Effect

Hullo Experts. I have a Projection Server 2013 event every bit follows: we are seeing the task "Notes" field in the PWA site being cutting off and, instead of the older notes, we meet wierd characters such as "05-30-13 SDP1.  Updated the ones that we coul@?"" or "[Pa??".  If nosotros check out the Project and view the notes they are all at that place merely not in PWA. Has anyone seen such a affair? Thanks very much for any help or direction.

Sometimes the field Locked cannot be updated in the view Close Tasks to Update in Projection Server 2013

When attempting to edit a projection in the PWA I receive the mistake: 'An fault occurred while opening your project. Give us a few minutes and try again...' Projection Server 2013

Hello,

I am hoping someone can assist with the mistake nosotros are encountering when trying to edit a project from the PWA in Project Server 2013.  I can click on the projection name and go to the detail page and I tin can click and run into the schedule.  Notwithstanding, if I click on a task in the schedule and endeavour to edit it, I receive the post-obit fault:

'An mistake occurred while opening your project. Give us a few minutes and endeavour once more. If this happens once more, contact your administrator.'

At this point I must click cancel twice to get rid of the error popular-upwardly message.  At this bespeak, I am no longer able to look at the schedule of the project either.  Can someone assistance with this issue?

Thanks

howardequother.blogspot.com

Source: https://microfilaria4.rssing.com/chan-3737719/all_p244.html

0 Response to "An Error Occurred While Opening Your Project Give Us a Few Minutes and Try Again"

Post a Comment

Iklan Atas Artikel

Iklan Tengah Artikel 1

Iklan Tengah Artikel 2

Iklan Bawah Artikel